 Chesterford Science Village prefabricated packaged plantrooms totalled 17. with a minimal footprint Constant Air Systems designed and developed a scheme in which we could install all of the equipment our client required in the smallest space possible. With a small installation period CAS moved quickly to procure all of the equipment and get the delivery dates to be as short as possible with this achieved we set about the installation of the equipment.


 Photo of Skid just been delivered measuring 1800mm W x 600mm D x 2200mm H

 Final 8no skids ready for installation

 1st batch of units progressing well
 Close up view of single unit

Day 7 of first batch of skids 

 Photo of single unit on day 5 of installation
 Pump installed