Wednesday, 20 July 2011

BAE Barrow in Furness July 2011

BAE Systems
Barrow in Furness
Prefabricated Plantroom


  • Weatherproof enclosure 2.75 x 2.2 x 2.7 meters high
  • 2no.off gas fired boilers Quintas pro's
  • Boiler flue systems & combustion louvres
  • 2no.off LTHW circulation pumps single head as duty/standby
  • Pressurisation Unit complete with expansion vessel
  • All pipework installation fitout (including supply of 50mm dia GSV)
  • Factory supplied pipe services thermal insulation
  • Electrical services, Lighting/emergency & small power requirements
  • Electrical wiring installation of free issue control panel & losse controls
  • Preliminaries, design development & delivery to site via Hiab lorry.


 
 














Friday, 6 May 2011

Carnaby Street

Carnaby Street
Prefabricated Packaged Plantroom

Here is Carnaby Streets completed Packaged Plant room. Measuring 2.5 x 2.0 x 2.4 meters high.
Inside the LTHW Plantroom we have installed
2no.off Wall Hung Boilers c/w Flue System
1no.off Twin Head Pump
Type: Tped 32-120/2 (0.37kW)
All Relevant Pipe Services and Insulation
Preliminaries, Design Development & Site Delivery
All of this in a construction time of just 6-8 weeks.

Final commissioning due to be completed once positioning on site has been finalised.