Waitrose Guildford Prefabricated Packaged Plantroom moves closer to completion - 25th September 2015





Equipment Installed:

  • 2No. Gas 210 Pro Natural gas fired boilers manufactured by Remeha 
  • 2No. LTHW Stratos 40/1-8 Single head wilo pumps c/w inverters
  • 1No. LTHW DL-E 4-/170-5.5/2 twin head wilo circulating pump c/w inverters
  • 1No. HWS TOP-Z 25/6 single head wilo pump c/w fixed speed
  • 2No. CHW IL65/220-3/4 single head wilo circulation pumps 
  • 2No. CHW IL-E 50/170-7.5/2 twin head wilo circulation pumps c/w inverters
  • Above pumps to be installed with flexible pump connections 
  • 1No. LTHW Pressurisation unit Microfill EFD 300 c/w 300 litre expansion vessel
  • 2No. 8 Litre expansion vessels
  • 1No CHW Pressurisation unit Microfill EFD 200 c/w 200 litre expansion vessel
  • 2No. LTHW / CHW 6 Litre dosing pots 
  • 1No. 65mm Air/Dirt Separator
  • 1No. 80mm Air/Dirt Separator 
  • 1No. 100mm Air/Dirt Separator
  • 1No. Andrews EcoFlo natural gas fired water heater
  • 1No Grundfos Homebooster 4.5