Wednesday 30 January 2013

Martin Baker PPR January 2013


Progress of Martin Baker PPR

Constant Air Systems are delighted to construct another Prefabricated Plant-room  which shall be delivered within Oxfordshire.
Constant Air Systems worked hand in hand with the consultants to ensure that the customer was guaranteed the perfect product. 


















This Prefabricated Plant-room is fitted with;
        • A 6Litre Dosing Pot
        • An Electric Boiler
        • Thermal Insulation Has Been Applied
        • Magna 3 D40-80F                           Duty: 1.36 l/s @15kPa
        • Magna 3 D40-80F                           Duty: 0.552 l/s @45kPa
        • 80 Litre Horizontal Expansion Vessel
        • An Impress Standard Twin Pump Pressurisation Unit along with Commissioning
        • A Single Door
        • 500wide x 500high External Weather Louvre
        • 500wide x 250high External Weather Louvre